Substation Scout

Whitley, IN interconnection queue

0 active projects totalling 0 MW in the PJM queue, plus 10 with terminal status (shown greyed).

0active projects
0active MW
10total filed
Queue IDProjectkVMWResourceStatus
AG2-173 Twin Branch-Meridian 345 kV 345 120 Solar Withdrawn
AH1-298 Meridian 345 kV 345 75 Battery Withdrawn
AI2-162 Meridian - Twin Branch 345 kV 345 48 Solar Withdrawn
AE2-236 Dover Solar Facility 138 38.5 Solar Pending Termination
AG1-417 Gateway 69 kV 69 30 Solar Withdrawn
AG1-418 Gateway 69 kV 69 30 Solar Withdrawn
W3-024 Columbia 138kV 138 19.4 Wind Withdrawn
W2-044 Columbia 138kV 138 13.1 Wind Withdrawn
AI2-412 Gateway 69 kV 69 12 Solar Withdrawn
AI2-413 Gateway 69 kV 69 12 Solar Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.