Warren, NC interconnection queue
2 active projects totalling 92.5 MW in the PJM queue, plus 1 with terminal status (shown greyed).
2active projects
92.5active MW
3total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| AG2-522 | Five Forks DP - Littleton DP 115 kV | 115 | 48 | Solar | Active |
| AC1-054 | Hawtree Creek | 115 | 44.5 | Solar | In Service |
| AA2-169 | Five Forks Solar | 115 | 13.7 | Solar | Withdrawn |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.