Substation Scout

Unknown, KY interconnection queue

0 active projects totalling 0 MW in the PJM queue, plus 4 with terminal status (shown greyed).

0active projects
0active MW
4total filed
Queue IDProjectkVMWResourceStatus
AD1-134 JK Smith 138 kV 138 72.9 Gas Withdrawn
Y3-031A_EKPC2 Flemingsburg 138 KV 138 19.5 Wind Withdrawn
AG1-217 Cent Hardin-Kargle 69 kV Upgrade 69 0 Not reported Withdrawn
AG1-492 Kargle to Elizabethtown 69 kV 69 0 Not reported Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.