0 active projects totalling 0 MW in the PJM queue, plus 4 with terminal status (shown greyed).
0active projects
0active MW
4total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| O06 | Ft. Martin Pruntytown | n/r | 500 | Not reported | Withdrawn |
| C01-1716 | Pruntytown - Union Road 138 kV | 138 | 30 | Hydro | Withdrawn |
| W2-005 | Pruntytown 138kV | 138 | 30 | Hydro | Withdrawn |
| X2-008 | Pruntytown 138kV | 138 | 30 | Hydro | Withdrawn |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.