Sullivan, TN interconnection queue
0 active projects totalling 0 MW in the PJM queue, plus 3 with terminal status (shown greyed).
0active projects
0active MW
3total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| O58 | Tenn Eastman 138kV | 138 | 75 | Coal | Withdrawn |
| AA1-032 | Kingsport Mill | n/r | 45 | Other | Deactivated |
| P42 | West Kingsport | 138 | 45 | Other | Deactivated |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.