Stark, OH interconnection queue
1 active project totalling 200 MW in the PJM queue, plus 7 with terminal status (shown greyed).
1active projects
200active MW
8total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| AH1-752 | Not reported | n/r | 400 | Battery | Withdrawn |
| C01-2253 | Wagenhals 138 kV | 138 | 200 | Battery | Active |
| AG1-239 | Stark Solar | 138 | 90 | Solar | Withdrawn |
| AH1-655 | SE Canton 138 kV | 138 | 60 | Solar | Withdrawn |
| AH1-350 | Sunnyside – Carrolton 138 kV | 138 | 55.4 | Solar | Withdrawn |
| AG2-031 | East Canton-Robertsville 69 kV | 69 | 22.4 | Solar | Withdrawn |
| AE2-204 | Bolivar Solar | 34.5 | 9.3 | Solar | Withdrawn |
| AE2-195 | Robertsville PV I | 69 | 9 | Solar | Withdrawn |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.