Stark, OH interconnection queue

1 active project totalling 200 MW in the PJM queue, plus 7 with terminal status (shown greyed).

1active projects
200active MW
8total filed
Queue IDProjectkVMWResourceStatus
AH1-752 Not reported n/r 400 Battery Withdrawn
C01-2253 Wagenhals 138 kV 138 200 Battery Active
AG1-239 Stark Solar 138 90 Solar Withdrawn
AH1-655 SE Canton 138 kV 138 60 Solar Withdrawn
AH1-350 Sunnyside – Carrolton 138 kV 138 55.4 Solar Withdrawn
AG2-031 East Canton-Robertsville 69 kV 69 22.4 Solar Withdrawn
AE2-204 Bolivar Solar 34.5 9.3 Solar Withdrawn
AE2-195 Robertsville PV I 69 9 Solar Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.