Russell, KY interconnection queue
1 active project totalling 36 MW in the PJM queue, plus 3 with terminal status (shown greyed).
1active projects
36active MW
4total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| AG2-676 | Russell Co 161 kV | 161 | 90 | Solar | Withdrawn |
| AG2-677 | Russell Co J - Jamestown T 161 kV | 161 | 90 | Solar | Withdrawn |
| AF1-038 | Mt Olive Creek Solar | 69 | 36 | Solar | Under Construction |
| AG2-158 | Not reported | n/r | 15 | Hybrid | Withdrawn |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.