Substation Scout

Richland, OH interconnection queue

0 active projects totalling 0 MW in the PJM queue, plus 6 with terminal status (shown greyed).

0active projects
0active MW
6total filed
Queue IDProjectkVMWResourceStatus
AH1-609 Milliron-Brookside 138kV 138 101 Solar Withdrawn
AH2-374 Milliron - Brookside 138 kV II 138 84 Battery Withdrawn
X3-037 Krendale-Seneca 138kV 138 46 Not reported Withdrawn
AH1-608 Milliron-Brookside 138kV 138 29.6 Solar Withdrawn
U4-001 Black Fork Wind 138 26 Wind Withdrawn
W4-021A Richland & Crawford n/r 26 Wind Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.