Passaic, NJ interconnection queue

1 active project totalling 0.2 MW in the PJM queue, plus 6 with terminal status (shown greyed).

1active projects
0.2active MW
7total filed
Queue IDProjectkVMWResourceStatus
V4-028 Kuller Road SP 13.2 1.5 Solar Withdrawn
AE2-165 Cedar Grove 13.2 kV 13.2 1.1 Solar Withdrawn
W4-059 Metro Division Headquarters 13 0.2 Solar In Service
AD1-005 Jackson Road 480V n/r 0 Gas Withdrawn
AD1-009 Saddle Brook 480V n/r 0 Gas Withdrawn
AD1-010 McLean 480V n/r 0 Gas Withdrawn
AD1-011 Atheina 480V n/r 0 Gas Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.