Montgomery, VA interconnection queue
1 active project totalling 32 MW in the PJM queue, plus 4 with terminal status (shown greyed).
1active projects
32active MW
5total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| AE2-280 | Claytor Lake-Edgemont 138 kV | 138 | 76 | Solar | Withdrawn |
| AG2-604 | Edgemont 138 kV | 138 | 63 | Hybrid | Withdrawn |
| AG2-518 | Tech Drive 138 kV | 138 | 32 | Battery | Active |
| AI2-145 | Claytor Lake - Edgemont 138 kV | 138 | 30.4 | Solar | Withdrawn |
| W3-010 | Hans Meadow 12.47KV | 12.5 | 0 | Gas | Withdrawn |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.