Montgomery, KY interconnection queue
1 active project totalling 18 MW in the PJM queue, plus 5 with terminal status (shown greyed).
1active projects
18active MW
6total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| AI1-159 | Mount Sterling - Sideview 69 kV | 69 | 35 | Hybrid | Withdrawn |
| AG1-208 | Sideview-Mt Sterling 69 kV | 69 | 21.9 | Solar | Withdrawn |
| AG2-081 | Avon - Renaker 138 kV | 138 | 18 | Solar | Active |
| AG1-381 | Hope 69 kV | 69 | 17.4 | Solar | Withdrawn |
| AG2-671 | Hope - Frenchburg 69 kV | 69 | 11.9 | Solar | Withdrawn |
| AH1-464 | Hinkston 24.9 kV | 24.9 | 7.2 | Solar | Withdrawn |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.