Mercer, IL interconnection queue
1 active project totalling 40 MW in the PJM queue.
1active projects
40active MW
1total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| P11 | Bishop Hill WF | 138 | 40 | Wind | In Service |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.