0 active projects totalling 0 MW in the PJM queue, plus 1 with terminal status (shown greyed).

0active projects
0active MW
1total filed
Queue IDProjectkVMWResourceStatus
X3-053 Homer-Seville 69kV 69 6.7 Solar Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.