Mahoning, OH interconnection queue
0 active projects totalling 0 MW in the PJM queue, plus 3 with terminal status (shown greyed).
0active projects
0active MW
3total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| AH1-639 | Lordstown - Mansfield 345 kV | 345 | 150 | Hybrid | Withdrawn |
| AG2-591 | Bluebell-Sancap Tap 69 kV | 69 | 36.6 | Solar | Withdrawn |
| W4-001A_AT9 | Carbon Limestone Landfil Gas to Electricity Facility | 69 | 3.2 | Gas | Deactivated |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.