Logan, OH interconnection queue
1 active project totalling 21.3 MW in the PJM queue, plus 19 with terminal status (shown greyed).
1active projects
21.3active MW
20total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| AI2-081 | Marysville - Sorenson 765 kV | 765 | 271 | Solar | Withdrawn |
| AG1-003 | Grange Solar | 765 | 226 | Hybrid | Withdrawn |
| AF2-137 | Grange Solar | 765 | 210 | Solar | Withdrawn |
| AG1-004 | Grange Solar | 765 | 200 | Battery | Withdrawn |
| AH2-147 | Marysville - Sorenson 765 kV | 765 | 108.4 | Hybrid | Withdrawn |
| AG2-013 | Marysville-Sorenson 765 kV | 765 | 84 | Solar | Withdrawn |
| AH1-320 | Blue Jacket - Kirby 138 kV | 138 | 69 | Battery | Withdrawn |
| AI2-146 | Blue Jacket - Kirby 138 kV | 138 | 67.1 | Solar | Withdrawn |
| AH2-010 | Marysville - Sorenson 765 kV | 765 | 60 | Solar | Withdrawn |
| AF1-270 | Blue Jacket-Kirby 138 kV | 138 | 50 | Solar | Withdrawn |
| AH1-416 | Bellefontaine 69 kV | 69 | 50 | Hybrid | Withdrawn |
| AG1-323 | Bellefontaine PV and BESS Project | 138 | 40 | Hybrid | Withdrawn |
| AH1-198 | Marysville - Sorenson 765 kV | 765 | 33 | Solar | Withdrawn |
| AH1-219 | Blue Jacket 138 kV | 138 | 23.9 | Hybrid | Withdrawn |
| AH1-328 | Blue Jacket - Kirby 138 kV | 138 | 21.3 | Solar | Active |
| S51 | E. Liberty-Blue Jacket 69kV | 69 | 19.8 | Wind | Withdrawn |
| T154 | Cherokee Run LF | 69 | 10 | Gas | Deactivated |
| O21 | Liberty 69kV | 69 | 9.6 | Wind | Withdrawn |
| R50 | Liberty - Blue Jacket 69kV | 69 | 9.6 | Wind | Withdrawn |
| AG1-493 | Blue Jacket to Blue Jacket Tap 69 kV | 69 | 0 | Not reported | Withdrawn |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.