1 active project totalling 21.3 MW in the PJM queue, plus 19 with terminal status (shown greyed).

1active projects
21.3active MW
20total filed
Queue IDProjectkVMWResourceStatus
AI2-081 Marysville - Sorenson 765 kV 765 271 Solar Withdrawn
AG1-003 Grange Solar 765 226 Hybrid Withdrawn
AF2-137 Grange Solar 765 210 Solar Withdrawn
AG1-004 Grange Solar 765 200 Battery Withdrawn
AH2-147 Marysville - Sorenson 765 kV 765 108.4 Hybrid Withdrawn
AG2-013 Marysville-Sorenson 765 kV 765 84 Solar Withdrawn
AH1-320 Blue Jacket - Kirby 138 kV 138 69 Battery Withdrawn
AI2-146 Blue Jacket - Kirby 138 kV 138 67.1 Solar Withdrawn
AH2-010 Marysville - Sorenson 765 kV 765 60 Solar Withdrawn
AF1-270 Blue Jacket-Kirby 138 kV 138 50 Solar Withdrawn
AH1-416 Bellefontaine 69 kV 69 50 Hybrid Withdrawn
AG1-323 Bellefontaine PV and BESS Project 138 40 Hybrid Withdrawn
AH1-198 Marysville - Sorenson 765 kV 765 33 Solar Withdrawn
AH1-219 Blue Jacket 138 kV 138 23.9 Hybrid Withdrawn
AH1-328 Blue Jacket - Kirby 138 kV 138 21.3 Solar Active
S51 E. Liberty-Blue Jacket 69kV 69 19.8 Wind Withdrawn
T154 Cherokee Run LF 69 10 Gas Deactivated
O21 Liberty 69kV 69 9.6 Wind Withdrawn
R50 Liberty - Blue Jacket 69kV 69 9.6 Wind Withdrawn
AG1-493 Blue Jacket to Blue Jacket Tap 69 kV 69 0 Not reported Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.