Lehigh, PA interconnection queue

0 active projects totalling 0 MW in the PJM queue, plus 2 with terminal status (shown greyed).

0active projects
0active MW
2total filed
Queue IDProjectkVMWResourceStatus
AF2-281 LH-Decatur 13.2 0 Hybrid Withdrawn
AG1-157 Macungie-Emmaus Tie 69 kV 69 0 Solar Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.