Substation Scout

Knott, KY interconnection queue

2 active projects totalling 246 MW in the PJM queue, plus 2 with terminal status (shown greyed).

2active projects
246active MW
4total filed
Queue IDProjectkVMWResourceStatus
S56 Beaver Creek-Hazard 138kV 138 535 Coal Withdrawn
AG2-184 Harbert Metering 138 kV 138 126 Solar Active
AH1-617 Harbert Metering 138 kV 138 120 Solar Active
AG2-678 Vicco - Beckham 138 kV 138 72 Solar Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.