Substation Scout

Garrard, KY interconnection queue

1 active project totalling 30 MW in the PJM queue, plus 2 with terminal status (shown greyed).

1active projects
30active MW
3total filed
Queue IDProjectkVMWResourceStatus
AG1-526 Garrard Solar 345 133.2 Solar Withdrawn
AG2-687 Garrard 345 kV 345 129 Solar Withdrawn
AE2-254 Turkey Creek Solar 69 30 Solar In Service

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.