City of Fredericksburg, VA interconnection queue

0 active projects totalling 0 MW in the PJM queue, plus 2 with terminal status (shown greyed).

0active projects
0active MW
2total filed
Queue IDProjectkVMWResourceStatus
Y1-021 Fredericksburg-Cranes Corner 230kV 230 64 Not reported Withdrawn
X3-064 Fredericksburg-Mine Road 230kV 230 0 Not reported Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.