Substation Scout

Camden, NC interconnection queue

1 active project totalling 13 MW in the PJM queue, plus 4 with terminal status (shown greyed).

1active projects
13active MW
5total filed
Queue IDProjectkVMWResourceStatus
AA2-162 Elizabeth City-Shawboro 230kV 230 56 Solar Withdrawn
W3-066 Hales Lake Energy Center 230 40 Wind Withdrawn
AB2-022 Elizabeth City Solar 34.5 13 Solar In Service
AB2-081 Sligo 34.5kV 34.5 13 Solar Withdrawn
AB1-156 Sligo 34.5kV 34.5 7.6 Solar Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.