Butler, PA interconnection queue

1 active project totalling 250 MW in the PJM queue, plus 12 with terminal status (shown greyed).

1active projects
250active MW
13total filed
Queue IDProjectkVMWResourceStatus
C01-2165 Keisters 138 kV 138 250 Battery Active
Z1-037 Krendale-Shanor Manor 138kV 138 43 Not reported Withdrawn
AG1-420 Campbell-Kiesters 138 kV 138 42 Solar Withdrawn
AF1-271 Keisters-Krendale 138 kV 138 36 Solar Withdrawn
AE2-191 Saxonburg 138 kV 138 21.8 Solar Withdrawn
AI2-415 Campbell-Kiesters 138 kV 138 20.3 Solar Withdrawn
AE2-189 Housenville 138 kV 138 17.6 Solar Withdrawn
AH2-161 Prospect 25 kV 25 12.3 Solar Withdrawn
I16 Atwell 25kV 25 9.9 Gas Withdrawn
AI1-095 Branchron - Keisters 25 kV 25 8.4 Solar Withdrawn
AI2-485 Bruin Junction - Petrol Junction 25 kV 25 8.4 Solar Withdrawn
AG2-267 Branchton 12.47 kV 12.5 6.2 Solar Withdrawn
W1-107 Grove City Road 12kV 12 0.7 Solar Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.