Substation Scout

Ashtabula, OH interconnection queue

1 active project totalling 6.5 MW in the PJM queue, plus 8 with terminal status (shown greyed).

1active projects
6.5active MW
9total filed
Queue IDProjectkVMWResourceStatus
C01-1871 Erie West - Ashtabula 345 kV 345 198.6 Wind Withdrawn
I02 Erie West-Ashtabula 345kV 345 35 Gas Withdrawn
AG2-243 Rome-Orwell 36 kV 36 12 Solar Withdrawn
AG2-244 Winfield-Presrite Corp 36 kV 36 12 Solar Withdrawn
AH1-424 Sandborn 34.5 kV 34.5 11.5 Solar Withdrawn
W1-070A_AT4 Ashtabula 138kV 138 6.5 Wind Withdrawn
Y1-012 Geneva Renewable Energy Facility n/r 6.5 Gas In Service
AH2-073 Ashtabula County PV Project 2 n/r 2.1 Solar Withdrawn
AH2-074 Ashtabula County PV Project 1 n/r 2.1 Solar Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.