Adams, IN interconnection queue
1 active project
totaling 81 MW in the PJM queue, plus 5 with terminal status (shown grayed).
1 active projects
81 active MW
6 total filed
Queue ID Project kV MW Resource Status
AG1-225
Adams 138 kV
138
207
Solar
Withdrawn
C01-1777
Adams - Magley 138 kV
138
140
Battery
Withdrawn
AG1-232
Magley Solar Energy Center
138
81
Solar
Engineering and Procurement
AI2-168
Magley 138 kV
138
32.4
Solar
Withdrawn
R03
Adams - Allen 138kV
138
26
Wind
Withdrawn
AG2-242
Olive-University Park 345 kV
345
0
Not reported
Withdrawn
A request with terminal status left the queue as filed.
That is a record of the filing, not evidence of injection capacity at this location.
Confirm deliverability with PJM before relying on these figures.
Site Scanner draws on HIFLD substations and electric retail service
territories, newer substations HIFLD lacks from OpenStreetMap, EIA gas transmission pipelines, HIFLD gas facilities and gas
utility territories, USGS watershed boundaries, FEMA flood hazard layers and US Census
geocoding. Queue data is compiled from public interconnection
queue filings. Every figure carries its source and retrieval date.
A withdrawal records that a request left the queue. It says
nothing about injection capacity at that location. Verify with the relevant ISO before
relying on any figure. Queue datasets are tracked separately and are
not directly comparable: status vocabularies, fuel coding, and publication
cadence all differ.
Screening aid only. Not a system impact study. Contiguous US.