NV Energy request Company MV
NV Energy queue ID Company MV
Queue request Company MV was listed in the NV Energy interconnection queue at the end of 2025 as a 550 MW battery project in White Pine County, NV, according to Berkeley Lab’s queue data file. Its status as of December 31, 2025 was “Suspended”, with a proposed online date of December 31, 2030.
| Queue ID | Company MV |
|---|---|
| Project name | Not reported |
| Status (as published) | Suspended |
| Substation | Not reported |
| Point of interconnection | Not reported |
| County | White Pine |
| State | NV |
| Voltage | Not reported |
| Capacity | 550 MW |
| Resource (as published) | Battery |
| Resource category | Battery (normalized for filtering) |
| Proposed online date | 2030-12-31 |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
White Pine, NV: 26 requests in the NV Energy queue, 17 active totaling 7,599.9 MW.
Tracked changes
Not tracked. NV Energy rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Utility | NV Energy |
|---|---|
| Interconnection service | NRIS/ERIS |
| Project type | Generation |
| Queue date | 2022-03-28 |
Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.
Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.