Substation Scout

NV Energy request Company MG

NV Energy queue ID Company MG

Queue request Company MG was listed in the NV Energy interconnection queue at the end of 2025 as a 170 MW hybrid project in Humboldt County, NV, according to Berkeley Lab’s queue data file. Its status as of December 31, 2025 was “Active”, with a proposed online date of October 1, 2023.

Queue IDCompany MG
Project nameNot reported
Status (as published)Active
SubstationNot reported
Point of interconnectionNot reported
CountyHumboldt
StateNV
VoltageNot reported
Capacity170 MW
Resource (as published)Solar+Battery
Resource categoryHybrid (normalized for filtering)
Proposed online date2023-10-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Humboldt, NV: 28 requests in the NV Energy queue, 14 active totaling 3,946.6 MW.

Tracked changes

Not tracked. NV Energy rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityNV Energy
Interconnection serviceNRIS/ERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Queue date2021-09-30
Components (hybrid)Solar 170 MW + Battery

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first