14 active projects totaling 3,946.6 MW in the NV Energy queue, plus 14 with terminal status (shown grayed).
14active projects
3,946.6active MW
28total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| 25-00412 | Not reported | n/r | 600 | Other | Active |
| 25-00416 | Not reported | n/r | 600 | Hybrid | Active |
| Company NV | Not reported | n/r | 600 | Hybrid | Suspended |
| Company MF | Not reported | n/r | 500 | Hybrid | Withdrawn |
| Company PI | Not reported | n/r | 500 | Hybrid | Withdrawn |
| Company PJ | Not reported | n/r | 500 | Battery | Withdrawn |
| Company JL | Not reported | n/r | 400 | Hybrid | Withdrawn |
| Company PU | Not reported | n/r | 400 | Hybrid | Withdrawn |
| Company IF | Not reported | n/r | 350 | Solar | Active |
| Company OA | Not reported | n/r | 350 | Hybrid | Suspended |
| Company JM | Not reported | n/r | 300 | Hybrid | Withdrawn |
| Company JC | Not reported | n/r | 250 | Hybrid | Withdrawn |
| Company KN | Not reported | n/r | 250 | Hybrid | Active |
| Company QF | Not reported | n/r | 218.3 | Gas | Active |
| Company QG | Not reported | n/r | 218.3 | Gas | Active |
| 25-00410 | Not reported | n/r | 200 | Other | Active |
| 25-00411 | Not reported | n/r | 200 | Other | Active |
| Company MG | Not reported | n/r | 170 | Hybrid | Active |
| Company IG | Not reported | n/r | 150 | Solar | Active |
| Company IO | Not reported | n/r | 150 | Solar | Withdrawn |
| Company HZ | Not reported | n/r | 120 | Hybrid | Withdrawn |
| Company IK | Not reported | n/r | 120 | Hybrid | Withdrawn |
| Company JO | Not reported | n/r | 100 | Hybrid | Withdrawn |
| Company NG | Not reported | n/r | 100 | Hybrid | Withdrawn |
| Company OE | Not reported | n/r | 100 | Hybrid | Withdrawn |
| Company JD | Not reported | n/r | 70 | Hybrid | Withdrawn |
| 25N-SG3 | Not reported | n/r | 20 | Other | Active |
| 25N-SG4 | Not reported | n/r | 20 | Other | Active |