Substation Scout

Surplus; J495

MISO queue ID S1109

Surplus; J495 (S1109) was listed in the MISO interconnection queue at the end of 2025 as a 75 MW battery project in Kossuth County, IA, according to Berkeley Lab’s queue data file. The filing names Bison as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of September 30, 2026.

Queue IDS1109
Project nameSurplus; J495
Status (as published)Active
SubstationBison
Point of interconnectionBison
CountyKossuth
StateIA
VoltageNot reported
Capacity75 MW
Resource (as published)Battery
Resource categoryBattery (normalized for filtering)
Proposed online date2026-09-30
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Bison substation: 4 requests in the MISO queue, 3 active totaling 474.8 MW.

Queue IDProjectMWResourceStatus
J3522Not reported200SolarActive
J3157Not reported199.8WindActive
J1852Not reported200SolarWithdrawn

Kossuth, IA: 3 requests in the MISO queue, 2 active totaling 275 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityITC MIDWEST
Project typeGeneration
Queue date2025-07-11

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first