Substation Scout

Surplus; J1434

MISO queue ID S1101

Surplus; J1434 (S1101) was listed in the MISO interconnection queue at the end of 2025 as a 200 MW battery project in St. Francis County, AR, according to Berkeley Lab’s queue data file. The filing names BRINKLEY EAST - AECC AUBREY as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of October 31, 2027.

Queue IDS1101
Project nameSurplus; J1434
Status (as published)Active
SubstationBRINKLEY EAST - AECC AUBREY
Point of interconnectionBRINKLEY EAST - AECC AUBREY 230.0kV
CountySt. Francis
StateAR
Voltage230 kV
Capacity200 MW
Resource (as published)Battery
Resource categoryBattery (normalized for filtering)
Proposed online date2027-10-31
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

BRINKLEY EAST - AECC AUBREY substation: 3 requests in the MISO queue, 2 active totaling 375 MW.

Queue IDProjectMWResourceStatus
J2437Not reported175WindActive
J3584Not reported215BatteryWithdrawn

St. Francis, AR: 12 requests in the MISO queue, 5 active totaling 1,330.9 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityENTERGY ARKANSAS
Project typeGeneration
Queue date2025-06-16

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.