Substation Scout

Surplus; J1325

MISO queue ID S1078

Surplus; J1325 (S1078) was listed in the MISO interconnection queue at the end of 2025 as a 72 MW battery project in Rock County, MN, according to Berkeley Lab’s queue data file. The filing names Magnolia as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of June 15, 2027.

Queue IDS1078
Project nameSurplus; J1325
Status (as published)Active
SubstationMagnolia
Point of interconnectionMagnolia
CountyRock
StateMN
VoltageNot reported
Capacity72 MW
Resource (as published)Battery
Resource categoryBattery (normalized for filtering)
Proposed online date2027-06-15
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Magnolia substation: 3 requests in the MISO queue, 1 active totaling 72 MW.

Queue IDProjectMWResourceStatus
J1570Not reported200SolarWithdrawn
J3397Not reported80SolarWithdrawn

Rock, MN: 11 requests in the MISO queue, 6 active totaling 664 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityITC MIDWEST
Project typeGeneration
Queue date2025-02-18

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.