Duane Arnold (ARNOLD 5) substation interconnection queue
4 active projects totaling 615 MW in the MISO queue.
4 MISO queue filings name Duane Arnold (ARNOLD 5) as the point of interconnection, all in Linn County, IA.
4active projects
615active MW
4total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| R5071 | Replacing 244 MW of Solar with Nuclear; Duane Arnold | n/r | 251 | Nuclear | Active |
| R5069 | Replacing 200 MW of Solar with Nuclear; J1444 | n/r | 200 | Nuclear | Active |
| R5072 | Replacing 100 MW of Solar with Nuclear; Duane Arnold | n/r | 100 | Nuclear | Active |
| R5070 | Replacing 50 MW of Solar with Nuclear; Duane Arnold | n/r | 64 | Nuclear | Active |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.
Site Scanner