Substation Scout

Replacing 106 MW Coal with 106 MW BESS; Edwards Unit 3

MISO queue ID R1055

Replacing 106 MW Coal with 106 MW BESS; Edwards Unit 3 (R1055) was listed in the MISO interconnection queue at the end of 2025 as a 322 MW hybrid project in Peoria County, IL, according to Berkeley Lab’s queue data file. The filing names E.D. Edwards as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of September 30, 2025.

Queue IDR1055
Project nameReplacing 106 MW Coal with 106 MW BESS; Edwards Unit 3
Status (as published)Active
SubstationE.D. Edwards
Point of interconnectionE.D. Edwards 138kV
CountyPeoria
StateIL
Voltage138 kV
Capacity322 MW
Resource (as published)Other+Battery
Resource categoryHybrid (normalized for filtering)
Proposed online date2025-09-30
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

E.D. Edwards substation: 3 requests in the MISO queue, 1 active totaling 322 MW.

Queue IDProjectMWResourceStatus
R1054Replacing 261 MW Coal with 615 MW Solar; Edwards Unit 2261HybridWithdrawn
R1056Replacing 179 MW Coal with 179 MW Solar; Edwards Unit 3184.7HybridWithdrawn

Peoria, IL: 9 requests in the MISO queue, 8 active totaling 2,474 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityAMEREN ILLINOIS
Interconnection serviceNRIS
Project typeGeneration
Queue date2024-07-12
Components (hybrid)Other 322 MW + Battery

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.