Substation Scout

MISO request J4129

MISO queue ID J4129

Queue request J4129 was listed in the MISO interconnection queue at the end of 2025 as a 200 MW wind project in Otter Tail County, MN, according to Berkeley Lab’s queue data file. The filing names ALEXANDRIA - BISON as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of April 12, 2029.

Queue IDJ4129
Project nameNot reported
Status (as published)Active
SubstationALEXANDRIA - BISON
Point of interconnectionALEXANDRIA - BISON 345.0kV
CountyOtter Tail
StateMN
Voltage345 kV
Capacity200 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2029-04-12
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

ALEXANDRIA - BISON substation: 5 requests in the MISO queue, 5 active totaling 1,415 MW.

Queue IDProjectMWResourceStatus
J3762Not reported430SolarActive
J4091Not reported295SolarActive
J4147Not reported245SolarActive
J4148Not reported245SolarActive

Otter Tail, MN: 14 requests in the MISO queue, 7 active totaling 849.6 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityMISSOURI RIVER ENERGY SERVICES - TRANSMISSION
ClusterDPP Cycle Pending West
Interconnection serviceNRIS
Project typeGeneration
Queue date2025-10-01

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first