Queue request J4002 was listed in the MISO interconnection queue at the end of 2025 as a 200 MW battery project in Edgar County, IL, according to Berkeley Lab’s queue data file. The filing names 7KANSAS - 08SUGCRK as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of September 30, 2030.

Queue IDJ4002
Project nameNot reported
Status (as published)Active
Substation7KANSAS - 08SUGCRK
Point of interconnection7KANSAS - 08SUGCRK 345.0kV
CountyEdgar
StateIL
Voltage345 kV
Capacity200 MW
Resource (as published)Battery
Resource categoryBattery (normalized for filtering)
Proposed online date2030-09-30
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

7KANSAS - 08SUGCRK substation: 4 requests in the MISO queue, 4 active totaling 716.2 MW.

Queue IDProjectMWResourceStatus
J4003Not reported200SolarActive
J2266Not reported175HybridActive
J3797Not reported141.2SolarActive

Edgar, IL: 11 requests in the MISO queue, 5 active totaling 916.2 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityAMEREN TRANSMISSION COMPANY OF ILLINOIS
ClusterDPP Cycle Pending Central
Interconnection serviceNRIS
Project typeGeneration
Queue date2025-04-30

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first