MISO request J3986

MISO queue ID J3986

Queue request J3986 was listed in the MISO interconnection queue at the end of 2025 as a 270 MW solar project in Liberty County, TX, according to Berkeley Lab’s queue data file. The filing names JACINTO - PEACH CREEK as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of September 2, 2030.

Queue IDJ3986
Project nameNot reported
Status (as published)Active
SubstationJACINTO - PEACH CREEK
Point of interconnectionJACINTO - PEACH CREEK 230.0kV
CountyLiberty
StateTX
Voltage230 kV
Capacity270 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2030-09-02
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

JACINTO - PEACH CREEK substation: 2 requests in the MISO queue, 2 active totaling 475.8 MW.

Queue IDProjectMWResourceStatus
J3586Not reported205.8HybridActive

Liberty, TX: 17 requests in the MISO queue, 7 active totaling 1,250 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

ClusterDPP Cycle Pending South
Interconnection serviceNRIS
Project typeGeneration
Queue date2024-10-25

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.