Substation Scout

MISO request J3929

MISO queue ID J3929

Queue request J3929 was listed in the MISO interconnection queue at the end of 2025 as a 250 MW wind project in Audrain County, MO, according to Berkeley Lab’s queue data file. The filing names SPENCER CREEK as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of October 30, 2030.

Queue IDJ3929
Project nameNot reported
Status (as published)Active
SubstationSPENCER CREEK
Point of interconnectionSPENCER CREEK
CountyAudrain
StateMO
VoltageNot reported
Capacity250 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2030-10-30
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

SPENCER CREEK substation: 2 requests in the MISO queue, 2 active totaling 425 MW.

Queue IDProjectMWResourceStatus
J2288Not reported175SolarActive

Audrain, MO: 10 requests in the MISO queue, 2 active totaling 650 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityAMEREN MISSOURI
ClusterDPP Cycle Pending Central
Interconnection serviceNRIS
Project typeGeneration
Queue date2025-01-31

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.