SPENCER CREEK substation interconnection queue

2 active projects totaling 425 MW in the MISO queue.

2 MISO queue filings name SPENCER CREEK as the point of interconnection, all in MO.

2active projects
425active MW
2total filed
Queue IDProjectkVMWResourceStatus
J3929 Not reported n/r 250 Wind Active
J2288 Not reported n/r 175 Solar Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.