Substation Scout

MISO request J3681

MISO queue ID J3681

Queue request J3681 was listed in the MISO interconnection queue at the end of 2025 as a 300 MW wind project in Mclean County, IL, according to Berkeley Lab’s queue data file. The filing names 7CLINTON - 7BROKAW as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of April 1, 2028.

Queue IDJ3681
Project nameNot reported
Status (as published)Active
Substation7CLINTON - 7BROKAW
Point of interconnection7CLINTON - 7BROKAW 345.0kV
CountyMclean
StateIL
Voltage345 kV
Capacity300 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2028-04-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

7CLINTON - 7BROKAW substation: 2 requests in the MISO queue, 2 active totaling 600 MW.

Queue IDProjectMWResourceStatus
J2377Not reported300BatteryActive

Mclean, IL: 27 requests in the MISO queue, 11 active totaling 2,233 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityAMEREN ILLINOIS
ClusterDPP-2023 Central
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)In Progress (unknown study)
Study phase (as the queue printed it)Study Phase: DPP 1
Queue date2024-04-18

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.