Substation Scout

MISO request J3597

MISO queue ID J3597

Queue request J3597 was listed in the MISO interconnection queue at the end of 2025 as a 348 MW wind project in Lonoke County, AR, according to Berkeley Lab’s queue data file. The filing names WEST MEMPHIS EHV - KEO EHV as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of April 1, 2028.

Queue IDJ3597
Project nameNot reported
Status (as published)Active
SubstationWEST MEMPHIS EHV - KEO EHV
Point of interconnectionWEST MEMPHIS EHV - KEO EHV 500.0kV
CountyLonoke
StateAR
Voltage500 kV
Capacity348 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2028-04-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

WEST MEMPHIS EHV - KEO EHV substation: 8 requests in the MISO queue, 6 active totaling 2,067.5 MW.

Queue IDProjectMWResourceStatus
J2477Not reported600SolarActive
S1125Not reported400HybridActive
J3982Not reported319.5WindActive
J2482Not reported300SolarActive
J1820Not reported100SolarActive
J3303Not reported400SolarWithdrawn
J2649Not reported250HybridWithdrawn

Lonoke, AR: 24 requests in the MISO queue, 6 active totaling 1,387.5 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityENTERGY ARKANSAS
ClusterDPP-2023 South
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)In Progress (unknown study)
Study phase (as the queue printed it)Study Phase: DPP 1
Queue date2024-04-18

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner