6 active projects totaling 2,067.5 MW in the MISO queue, plus 2 with terminal status (shown grayed).

8 MISO queue filings name WEST MEMPHIS EHV - KEO EHV as the point of interconnection, all in AR.

6active projects
2,067.5active MW
8total filed
Queue IDProjectkVMWResourceStatus
J2477 Not reported 500 600 Solar Active
J3303 Not reported 500 400 Solar Withdrawn
S1125 Not reported 500 400 Hybrid Active
J3597 Not reported 500 348 Wind Active
J3982 Not reported 500 319.5 Wind Active
J2482 Not reported 500 300 Solar Active
J2649 Not reported 500 250 Hybrid Withdrawn
J1820 Not reported 500 100 Solar Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.