Queue request J2578 was listed in the MISO interconnection queue at the end of 2025 as a 180 MW solar project in Tuscola County, MI, according to Berkeley Lab’s queue data file. The filing names KARN - THETFORD (ATLANTA) as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of September 1, 2026.

Queue IDJ2578
Project nameNot reported
Status (as published)Active
SubstationKARN - THETFORD (ATLANTA)
Point of interconnectionKARN - THETFORD (ATLANTA) 138.0kV
CountyTuscola
StateMI
Voltage138 kV
Capacity180 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2026-09-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

KARN - THETFORD (ATLANTA) substation: 2 requests in the MISO queue, 2 active totaling 340 MW.

Queue IDProjectMWResourceStatus
J4047Not reported160SolarActive

Tuscola, MI: 25 requests in the MISO queue, 15 active totaling 2,038.6 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityMETC
ClusterDPP-2022 East (ITC)
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)Cluster Study
Study phase (as the queue printed it)Study Phase: DPP 2; Post GIA Status: Not Started
Queue date2022-09-13

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first