Substation Scout

KARN - THETFORD (ATLANTA) substation interconnection queue

2 active projects totaling 340 MW in the MISO queue.

2 MISO queue filings name KARN - THETFORD (ATLANTA) as the point of interconnection, all in Tuscola County, MI.

2active projects
340active MW
2total filed
Queue IDProjectkVMWResourceStatus
J2578 Not reported 138 180 Solar Active
J4047 Not reported 138 160 Solar Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first