Substation Scout

MISO request J2087

MISO queue ID J2087

Queue request J2087 was listed in the MISO interconnection queue at the end of 2025 as a 125 MW solar project in Renville County, MN, according to Berkeley Lab’s queue data file. The filing names FRANKLIN as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of November 30, 2024.

Queue IDJ2087
Project nameNot reported
Status (as published)Active
SubstationFRANKLIN
Point of interconnectionFRANKLIN
CountyRenville
StateMN
VoltageNot reported
Capacity125 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2024-11-30
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

FRANKLIN substation: 2 requests in the MISO queue, 1 active totaling 125 MW.

Queue IDProjectMWResourceStatus
J1700Not reported288SolarWithdrawn

Renville, MN: 12 requests in the MISO queue, 2 active totaling 325 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityNORTHERN STATES POWER COMPANY
ClusterDPP-2021 West
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)Cluster Study
Study phase (as the queue printed it)Study Phase: DPP 3; Post GIA Status: Not Started
Queue date2025-08-19

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →