Queue request J2055 was listed in the MISO interconnection queue at the end of 2025 as a 100 MW solar project in Sheboygan County, WI, according to Berkeley Lab’s queue data file. The filing names Edgewater as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of June 26, 2026.

Queue IDJ2055
Project nameNot reported
Status (as published)Active
SubstationEdgewater
Point of interconnectionEdgewater
CountySheboygan
StateWI
VoltageNot reported
Capacity100 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2026-06-26
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Edgewater substation: 3 requests in the MISO queue, 3 active totaling 826.6 MW.

Queue IDProjectMWResourceStatus
R1015Replacing 300 MW of existing coal generation with BESS; Edgewater 5423.1HybridActive
R1049Replacing 303.5 MW BESS with 303.5 MW COAL; Edgewater Unit 5303.5HybridActive

Sheboygan, WI: 11 requests in the MISO queue, 7 active totaling 1,603.3 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityAMERICAN TRANSMISSION COMPANY
ClusterDPP-2021 East (ATC)
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)In Progress (unknown study)
Study phase (as the queue printed it)Study Phase: Re-Study; Post GIA Status: Not Started
Queue date2021-08-13

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first