Substation Scout

MISO request J1067

MISO queue ID J1067

Queue request J1067 was listed in the MISO interconnection queue at the end of 2025 as a 240 MW solar project in Jasper County, IN, according to Berkeley Lab’s queue data file. The filing names Reynolds - Burr Oak Line as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of October 20, 2023.

Queue IDJ1067
Project nameNot reported
Status (as published)Active
SubstationReynolds - Burr Oak Line
Point of interconnectionReynolds - Burr Oak 345kV Line
CountyJasper
StateIN
Voltage345 kV
Capacity240 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2023-10-20
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Reynolds - Burr Oak Line substation: 3 requests in the MISO queue, 3 active totaling 500 MW.

Queue IDProjectMWResourceStatus
J2663Not reported200BatteryActive
S1028Surplus; J106760HybridActive

Jasper, IN: 19 requests in the MISO queue, 15 active totaling 6,134.5 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityNORTHERN INDIANA PUBLIC SERVICE COMPANY
ClusterDPP-2018-APR Central
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)Construction
Study phase (as the queue printed it)Study Phase: GIA; Post GIA Status: Under Construction
Queue date2018-03-12
Interconnection agreement date2021-10-12
Operational date2024-05-24

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.