Substation Scout

MISO request G809

MISO queue ID G809

Queue request G809 was listed in the MISO interconnection queue at the end of 2025 as a 193 MW gas project in Midland County, MI, according to Berkeley Lab’s queue data file. The filing names Tittabawassee Substation as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of December 1, 2009.

Queue IDG809
Project nameNot reported
Status (as published)Operational
SubstationTittabawassee Substation
Point of interconnectionTittabawassee 345kV Substation
CountyMidland
StateMI
Voltage345 kV
Capacity193 MW
Resource (as published)Gas
Resource categoryGas (normalized for filtering)
Proposed online date2009-12-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Tittabawassee Substation substation: 3 requests in the MISO queue, 1 active totaling 193 MW.

Queue IDProjectMWResourceStatus
G687Not reported750CoalWithdrawn
J234Not reported35OtherWithdrawn

Midland, MI: 17 requests in the MISO queue, 6 active totaling 993.2 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

ClusterDPP-2008-NOV MI
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)Network Upgrade
Queue date2007-06-12
Interconnection agreement date2010-07-08
Operational date2009-12-01

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first