Substation Scout

Midland, MI interconnection queue

6 active projects totaling 993.2 MW in the MISO queue, plus 11 with terminal status (shown grayed).

6active projects
993.2active MW
17total filed
Queue IDProjectkVMWResourceStatus
G687 Not reported 345 750 Coal Withdrawn
J275 Not reported 345 700 Gas Withdrawn
J3052 Not reported n/r 300 Gas Withdrawn
J1194 Not reported 138 225.2 Wind Operational
J1005 Not reported 345 200 Solar Withdrawn
J1515 Not reported 345 200 Solar Withdrawn
J1913 Not reported 345 200 Solar Withdrawn
J2877 Not reported 345 200 Solar Active
G809 Not reported 345 193 Gas Operational
J2494 Not reported 138 178 Solar Withdrawn
J3059 Not reported n/r 175 Solar Active
J3776 Not reported n/r 150 Battery Active
J2491 Not reported 138 100 Solar Withdrawn
J3643 Not reported 138 50 Battery Withdrawn
S1061 Surplus; G905 138 50 Hybrid Active
J234 Not reported n/r 35 Other Withdrawn
J3228 Not reported 138 26 Solar Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →