MISO request G566

MISO queue ID G566

Queue request G566 was listed in the MISO interconnection queue at the end of 2025 as a 3 MW wind project in Missaukee County, MI, according to Berkeley Lab’s queue data file. The filing names Cadillac - Leroy as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of June 1, 2011.

Queue IDG566
Project nameNot reported
Status (as published)Operational
SubstationCadillac - Leroy
Point of interconnectionCadillac - Leroy 69 kV
CountyMissaukee
StateMI
Voltage69 kV
Capacity3 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2011-06-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Cadillac - Leroy substation: 2 requests in the MISO queue, 2 active totaling 21 MW.

Queue IDProjectMWResourceStatus
G566dNot reported18WindOperational

Missaukee, MI: 4 requests in the MISO queue, 3 active totaling 66 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

ClusterG566 G566
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)Network Upgrade
Queue date2005-11-07
Interconnection agreement date2007-04-09
Operational date2011-06-01

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.