Substation Scout

MISO request G397

MISO queue ID G397

Queue request G397 was listed in the MISO interconnection queue at the end of 2025 as a 5 MW wind project in Pipestone County, MN, according to Berkeley Lab’s queue data file. The filing names Chanarambie as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of January 1, 2009.

Queue IDG397
Project nameNot reported
Status (as published)Operational
SubstationChanarambie
Point of interconnectionChanarambie 115kV
CountyPipestone
StateMN
Voltage115 kV
Capacity5 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2009-01-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Chanarambie substation: 3 requests in the MISO queue, 3 active totaling 15 MW.

Queue IDProjectMWResourceStatus
G382Not reported8WindOperational
G398Not reported2WindOperational

Pipestone, MN: 23 requests in the MISO queue, 12 active totaling 293.2 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

ClusterG397 G397
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)Network Upgrade
Queue date2004-01-22
Interconnection agreement date2005-03-25
Operational date2009-01-01

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first