Queue request G032 was listed in the MISO interconnection queue at the end of 2025 as a 95 MW hydro project in Hancock County, KY, according to Berkeley Lab’s queue data file. The filing names Cloverport Substation as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of June 1, 2001.

Queue IDG032
Project nameNot reported
Status (as published)Operational
SubstationCloverport Substation
Point of interconnectionCloverport 138 kV Substation
CountyHancock
StateKY
Voltage138 kV
Capacity95 MW
Resource (as published)Hydro
Resource categoryHydro (normalized for filtering)
Proposed online date2001-06-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Cloverport Substation substation: 2 requests in the MISO queue, 2 active totaling 179 MW.

Queue IDProjectMWResourceStatus
G849Not reported84HydroOperational

Hancock, KY: 5 requests in the MISO queue, 3 active totaling 345 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Queue date2000-03-01
Interconnection agreement date2003-11-14
Operational date2001-06-01

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first