3 active projects totaling 345 MW in the MISO queue, plus 2 with terminal status (shown grayed).

3active projects
345active MW
5total filed
Queue IDProjectkVMWResourceStatus
J3559 Not reported n/r 250 Battery Withdrawn
J3726 Not reported n/r 200 Battery Withdrawn
J1638 Not reported 161 150 Solar Active
S1083 Surplus; J1638 n/r 100 Battery Active
G032 Not reported 138 95 Hydro Operational

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.